Here’s what to expect with a 72-Hour Shower Conversion:
Tub-to-shower and shower-to-shower conversion
Scope:
This conversion will remove an existing shower and install a standard sized shower with 84" walls.
Measure:
One week prior to beginning work, a marble measure is scheduled and performed.
Day One:
- Tub and/or shower walls are removed down to the studs.
- The plumbing drain is positioned.
- Other plumbing revisions are completed, as necessary.
- Moisture rated backer board is installed.
Day Two:
- Shower wall panels are installed.
- Plumbing fixture trim is installed.
Day Three:
- Final inspections and clean-up.
Important:
- If standard cultured marble or acrylic is being removed, the drain location will fit a standard cultured marble shower pan and a two day conversion is possible.
- If tile is being removed and the shower drain is not in a standard location the plumber must relocate the drain per the cultured marble shower pan specification and may extend the time schedule.
- Any shower not a "standard shower size" option will be considered custom and not guaranteed in 72 hours.
- Please wait 24 hours after installation before using shower.
Completed within 72 hours of construction start date. Unforeseen material, supply or structural complications may extend completion date. Actual price may vary depending on the size and scope of the remodeling project. Based on approved credit. Applies to purchases made through John Moore Renovation credit program. *$62.49 monthly payment calculation based on a $4,999 purchase price at 9.99% APR on a payment factor of 1.25%.